Originally posted by WTFH View Post
YOU refused to work inside, so they terminated the contract.
They have terminated the contract because you have refuse to do the work. They even offered to increase your rate, but you didn't want it.
Therefore yes, they can do it.
Sure, you can take them to court, but it will be an expensive lesson for you, as the evidence you've presented here seems quite clear.
Good luck in your next gig.Then what is the notice period for? Can contractors do the same thing? Leave without notice?Originally posted by eek View Post
There is no work available under the old terms as the situation has changed.
Hence the end of your contract....Comment
-
Then there’s not much more to say. The agency got you in under false pretences (that you won’t be able to prove) and the client binned you when you refused the old switcheroo.
That’s it really."I can put any old tat in my sig, put quotes around it and attribute to someone of whom I've heard, to make it sound true."
- Voltaire/Benjamin Franklin/Anne Frank...Comment
-
Yes they can. I did when a project I was on got cancelled.Originally posted by sammy2020 View Post
Then what is the notice period for? Can contractors do the same thing? Leave without notice?"I can put any old tat in my sig, put quotes around it and attribute to someone of whom I've heard, to make it sound true."
- Voltaire/Benjamin Franklin/Anne Frank...Comment
-
They can't continue with the old contract with the company you are the director. So that contact is null and void. The only work available is under the new contact with you personally. You personally refused to accept the new terms so they have to now look for someone else.Originally posted by sammy2020 View Post
I didn't refuse to work. I refused new contract.
"You’re just a bad memory who doesn’t know when to go away" JRComment
-
It's likely the client didn't know what the agency was up to.Originally posted by cojak View PostThen there’s not much more to say. The agency got you in under false pretences (that you won’t be able to prove) and the client binned you when you refused the old switcheroo.
That’s it really."You’re just a bad memory who doesn’t know when to go away" JRComment
-
Nope - the notice period is there to allow you to leave and for agencies to provide a nicer notice period if it's practical - I had a lovely one years back where HP served notice to the agency, agency served notice on me and HP were surprised I was leaving the following Friday.Originally posted by sammy2020 View Post
Then what is the notice period for? Can contractors do the same thing? Leave without notice?
Agency had me on 1 weeks notice, HP had it as a month.
Cue a lot of panic as agency desperately tried to keep me on to finish the project due to their screw up (was a nice pay rise for the final 3 weeks work).
However the reality of any business to business contract is that I can replace you with someone else tomorrow if I have no work for you to do.merely at clientco for the entertainmentComment
-
No. You are in a client/supplier relationship. These things are not equal. They have the money and you work for it so it's going to be weighted in someone's favour I am afraid. Notice is to terminate the contract and, as mentioned before, they have terms in that say if you don't do work you don't get paid. In theory they should say, we've no more work for you so don't come in again and we will service notice on the contract to expire on XXX date. The notice period has been honoured but due to other clauses there is no more work. You earning money and the contract expiring are totally different things.Originally posted by sammy2020 View PostThen what is the notice period for? Can contractors do the same thing? Leave without notice?
Thankfully many clients will honour the notice or plan exit so it can be worked. In this case there has been such a fundamental shift in the contract then the old one is dead and you don't want to work under the terms of the new one so you are done.
Horrible mess and we've had a couple of other people in exactly the same situation as you. It's going to happen a lot. You really must get an SDS from the client before you start. The days of the agent saying it's outside and all that rubbish have gone. The SDS is the one document you need so get it before you start.
'CUK forum personality of 2011 - Winner - Yes really!!!!
Comment
-
Not quite - you need the SDS and separate confirmation from the end client that it is actually valid.Originally posted by northernladuk View Post
No. You are in a client/supplier relationship. These things are not equal. They have the money and you work for it so it's going to be weighted in someone's favour I am afraid. Notice is to terminate the contract and, as mentioned before, they have terms in that say if you don't do work you don't get paid. In theory they should say, we've no more work for you so don't come in again and we will service notice on the contract to expire on XXX date. The notice period has been honoured but due to other clauses there is no more work. You earning money and the contract expiring are totally different things.
Thankfully many clients will honour the notice or plan exit so it can be worked. In this case there has been such a fundamental shift in the contract then the old one is dead and you don't want to work under the terms of the new one so you are done.
Horrible mess and we've had a couple of other people in exactly the same situation as you. It's going to happen a lot. You really must get an SDS from the client before you start. The days of the agent saying it's outside and all that rubbish have gone. The SDS is the one document you need so get it before you start.
Remember - the biggest concern that JamesBrown and myself both have is that a determination may be changed well after you start work (and I'm not talking about 4 days here I'm talking nearly 4 months if it's monthly billing and 90 day terms).merely at clientco for the entertainmentComment
-
My reply in Gordon Ramsey mode. Why the f don't you read the small print! If you don't understand about contracts then f'ing spend £10 and download a f'ing book on Kindle that explains about contracts. Contract law is not as simplistic as many people think. Read and understand before signing even if the agent is sitting and waiting for you to do so. Don't be f'ing be shy for asking for T&Cs to be changed.Originally posted by sammy2020 View Post
I refused new terms. Contract clearly mentions that it is outside IR35. If they wanted me to work inside IR35, it will be a new contract. I was happy to work continue working under current terms."A people that elect corrupt politicians, imposters, thieves and traitors are not victims, but accomplices," George OrwellComment
- Home
- News & Features
- First Timers
- IR35 / S660 / BN66
- Employee Benefit Trusts
- Agency Workers Regulations
- MSC Legislation
- Limited Companies
- Dividends
- Umbrella Company
- VAT / Flat Rate VAT
- Job News & Guides
- Money News & Guides
- Guide to Contracts
- Successful Contracting
- Contracting Overseas
- Contractor Calculators
- MVL
- Contractor Expenses
Advertisers

Comment