Maybe I'm not cut out to be a contractor. LOL.
Valuable lesson learnt this contract about trusting client and not bothering to add stuff to contract. At the time, seemed a bit pedantic to go through all the rigmarole and gentlemans agreement seemed to suffice. Shifts were mentioned at interview but nothing was ever put into contract.
To be fair, at the beginning, client seemed to be dealing OK. Offered 1.5 for 12 hour shifts etc. But then it started to go wrong.
Client seemed to think they owned contractors for duration of contract. This led to them thinking that any changes (nights, weekends, 12 hours etc) could be done with as little notice as they saw fit (sometimes within 12 hours). Didn't happen to me but one guy turned up night shift at 8pm - they'd left note with security guard to tell him he wasn't needed that night after all!
They also seemed to think that 'additional' days were compulsory and not optional. i.e. If you worked mon-fri then they wanted you for the saturday then if they asked 3pm friday you could not say no.
Worst of all though. Seem to think that even if they did shift rota, you turned up to work the full shift, they could a week later say - we didn't need you to work 12 hours that day we're only signing timesheet for standard day. Even though no-one was told.
Next time I hear the words shift, I will be making sure I add the following to contract:-
1. 12 hour shifts are paid at a premium not a standard day.
2. Any changes to shifts must be notified at least 7 days in advance.
3. Any changes not communicated will be subject to payment as planned.
Sad that its come to this but it seems there are clients who cannot be trusted. :-(
Valuable lesson learnt this contract about trusting client and not bothering to add stuff to contract. At the time, seemed a bit pedantic to go through all the rigmarole and gentlemans agreement seemed to suffice. Shifts were mentioned at interview but nothing was ever put into contract.
To be fair, at the beginning, client seemed to be dealing OK. Offered 1.5 for 12 hour shifts etc. But then it started to go wrong.
Client seemed to think they owned contractors for duration of contract. This led to them thinking that any changes (nights, weekends, 12 hours etc) could be done with as little notice as they saw fit (sometimes within 12 hours). Didn't happen to me but one guy turned up night shift at 8pm - they'd left note with security guard to tell him he wasn't needed that night after all!
They also seemed to think that 'additional' days were compulsory and not optional. i.e. If you worked mon-fri then they wanted you for the saturday then if they asked 3pm friday you could not say no.
Worst of all though. Seem to think that even if they did shift rota, you turned up to work the full shift, they could a week later say - we didn't need you to work 12 hours that day we're only signing timesheet for standard day. Even though no-one was told.
Next time I hear the words shift, I will be making sure I add the following to contract:-
1. 12 hour shifts are paid at a premium not a standard day.
2. Any changes to shifts must be notified at least 7 days in advance.
3. Any changes not communicated will be subject to payment as planned.
Sad that its come to this but it seems there are clients who cannot be trusted. :-(
Comment