At the beginning of this year clientco asked me (as Programme and Project Manager) to take on portfolio A and portfolio B, with the proviso that workload at the projects ramped up would be monitored and additional resource would be brought in to satisfy additional load. My contract is "aligned" to portfolio B so if push came to shove, portfolio A would have the job of finding more resource as I would be fully focussed on porfolio B.
In Mid-March I produced a PM resource demand forecast which demonstrated 1 full time PM was required for both portfolios. Six weeks later nothing has demonstrably happened, and clientco are about to award a (three figure) contract for an external vendor to come into the company for six weeks to complete a due diligence phase on a project in portfolio A. This increases the load drastically on Portfolio A to the extent that it would be futile to even contemplate embarking on the exercise with anything other than a dedicated PM.
I have recommended to the client that they do not start this due diligence until a full-time PM is in place, as it is critical to the development of a global communication platform. I have also asked clientco to tell me which portfolio they would like me to prioritise my services on.
I got a wishy-washy reply from Director-portfolio A (who incidentally I would trust only to stab me in the back without a second thought), saying continue to prioritise my limited resources in a professional manner (and unofficially he has admitted that he knows it will fail but it will prove a point). The PMO director has said nothing. Director-portfolio B says "you are my service provider, you must deliver my projects, the resourcing is director-portfolio-A's problem". No-one will make a decision because no-one wants to be the one that "delays" the (board-level-visible) communication-platform project, so I am stuck in the middle of organisational politics with two portfolios proceeding towards failure.
I am extremely uncomfortable in proceeding "by default" with work I know will fail because it is not resourced effectively to deliver, regardless of the revenue it guarantees for a few weeks at least. I am (for convoluted supply chain reasons) unable to take on additional resource myself to address the issue.
Options:
1) Proceed by default, accept it will fail and all projects will suffer (result - reputational damage, I may escape without contract termination if I am lucky).
2) Politely refuse to take on the additional load in Portfolio. (result - I am seen as an "awkward" contractor when it comes to contract renewal/negotiation).
3)......I kind of run out there....
Advice please?
In Mid-March I produced a PM resource demand forecast which demonstrated 1 full time PM was required for both portfolios. Six weeks later nothing has demonstrably happened, and clientco are about to award a (three figure) contract for an external vendor to come into the company for six weeks to complete a due diligence phase on a project in portfolio A. This increases the load drastically on Portfolio A to the extent that it would be futile to even contemplate embarking on the exercise with anything other than a dedicated PM.
I have recommended to the client that they do not start this due diligence until a full-time PM is in place, as it is critical to the development of a global communication platform. I have also asked clientco to tell me which portfolio they would like me to prioritise my services on.
I got a wishy-washy reply from Director-portfolio A (who incidentally I would trust only to stab me in the back without a second thought), saying continue to prioritise my limited resources in a professional manner (and unofficially he has admitted that he knows it will fail but it will prove a point). The PMO director has said nothing. Director-portfolio B says "you are my service provider, you must deliver my projects, the resourcing is director-portfolio-A's problem". No-one will make a decision because no-one wants to be the one that "delays" the (board-level-visible) communication-platform project, so I am stuck in the middle of organisational politics with two portfolios proceeding towards failure.
I am extremely uncomfortable in proceeding "by default" with work I know will fail because it is not resourced effectively to deliver, regardless of the revenue it guarantees for a few weeks at least. I am (for convoluted supply chain reasons) unable to take on additional resource myself to address the issue.
Options:
1) Proceed by default, accept it will fail and all projects will suffer (result - reputational damage, I may escape without contract termination if I am lucky).
2) Politely refuse to take on the additional load in Portfolio. (result - I am seen as an "awkward" contractor when it comes to contract renewal/negotiation).
3)......I kind of run out there....
Advice please?
Comment