• Visitors can check out the Forum FAQ by clicking this link. You have to register before you can post: click the REGISTER link above to proceed. To start viewing messages, select the forum that you want to visit from the selection below. View our Forum Privacy Policy.
  • Want to receive the latest contracting news and advice straight to your inbox? Sign up to the ContractorUK newsletter here. Every sign up will also be entered into a draw to WIN £100 Amazon vouchers!
Collapse

You are not logged in or you do not have permission to access this page. This could be due to one of several reasons:

  • You are not logged in. If you are already registered, fill in the form below to log in, or follow the "Sign Up" link to register a new account.
  • You may not have sufficient privileges to access this page. Are you trying to edit someone else's post, access administrative features or some other privileged system?
  • If you are trying to post, the administrator may have disabled your account, or it may be awaiting activation.

Previously on "Uneven notice period advice"

Collapse

  • PerfectStorm
    replied
    Originally posted by Arc1 View Post
    Mine would be going from 20 days down t o10
    Same - sometimes you want to leave and you don't want to hang about doing it! 7/14 is ideal.

    Leave a comment:


  • northernladuk
    replied
    Originally posted by Arc1 View Post
    Mine would be going from 20 days down t o10
    Ah yes. I see now.

    Leave a comment:


  • Arc1
    replied
    Mine would be going from 20 days down t o10

    Leave a comment:


  • northernladuk
    replied
    Zero days notice is best for IR35 as proven in case law.

    Above that any notice period is pretty neutral for IR35 and irrelevant anyway as they can just withdraw work from you while whatever notice carries on effectively being instant to you.

    Just get the shortest one possible in case you need to leave. Increase yours from 10 to 20 is a tad silly.

    Leave a comment:


  • Yuri F
    replied
    Business relations normally imply much higher risks and less rights
    I personally tend to push into immediate termination by client
    and longer termination by my ltd (supplier).
    More unfair balance (less protection for you) - less risks to get inside IR35.

    Leave a comment:


  • eek
    replied
    Originally posted by Arc1 View Post
    Hi,

    In my existing contract I had the agency amend the notice period from 20 days client, 10 days contractor, to which the client agreed on a 20/20 even split.

    I requested this as I believed an even period would be better for outside IR35 purposes

    I am about to enter a renewal, and the client has requested it be brought back to 20/10 split to bring it back in line with their standard contracts.

    This is for a 3 month renewal, when I have been there 12 months already

    Should I be concerned, and does this look bad from an IR35 perspective?

    Thanks

    Arc
    What has notice periods got to do with IR35?

    Leave a comment:


  • Arc1
    started a topic Uneven notice period advice

    Uneven notice period advice

    Hi,

    In my existing contract I had the agency amend the notice period from 20 days client, 10 days contractor, to which the client agreed on a 20/20 even split.

    I requested this as I believed an even period would be better for outside IR35 purposes

    I am about to enter a renewal, and the client has requested it be brought back to 20/10 split to bring it back in line with their standard contracts.

    This is for a 3 month renewal, when I have been there 12 months already

    Should I be concerned, and does this look bad from an IR35 perspective?