I had 9 days to virtualise and migrate 18 servers to a new datacentre, as the current site hosting the servers is shutting
I've just finished testing everything after a long 3 days, yesterday was a bitch start at 7:30 am finish at 10pm and then start again at 7am this morning
For someone who usually does development work, it was a bind to get lumped with it, but for once I still the credit
Now quaffing pints of Tanglefoot and living the dream
I've just finished testing everything after a long 3 days, yesterday was a bitch start at 7:30 am finish at 10pm and then start again at 7am this morning
For someone who usually does development work, it was a bind to get lumped with it, but for once I still the credit
Now quaffing pints of Tanglefoot and living the dream