What a waste of 7 pages and 70 odd threads.
The answer is simply, would the software team without a PM;
- be able to manage the initial phases - project setup, reqs/design activity ?
- be able to know what additional numbers to include in the costs in addition to what what they are developing as the
software team - infrastructure, training, resourcing ?
- monitor the budget ?
- be able to manage phases of testing - system, user, nft etc ?
- be able to oversee training to users
- also arrange user logons
- what about rollout approach
- go live cutover, making sure everything is signed off
- manage stakeholders, especially those emedded in the business who are only want to know how much and when, as opposed to what development technologies are being used ?
In my experience I don't think so.
The answer is simply, would the software team without a PM;
- be able to manage the initial phases - project setup, reqs/design activity ?
- be able to know what additional numbers to include in the costs in addition to what what they are developing as the
software team - infrastructure, training, resourcing ?
- monitor the budget ?
- be able to manage phases of testing - system, user, nft etc ?
- be able to oversee training to users
- also arrange user logons
- what about rollout approach
- go live cutover, making sure everything is signed off
- manage stakeholders, especially those emedded in the business who are only want to know how much and when, as opposed to what development technologies are being used ?
In my experience I don't think so.