Hi all,
Had an interesting experience with a client yesterday. I have a 3 month contract with them, which has started to roll over because the work is far more extensive than what could be completed in time, so i'm in the 4th month of it at the moment, and they are quite happy with that.
I get an email from the Project Manager telling me to stop work on my current project for a couple of days to add some high priority features to a different project. This other project is a project I developed for them last year, but that contract has long ended, and my current work schedule only describes work on my current project.
The problem is I had to refuse to do this other work, as them telling me what to work on and when (especially outside of the work schedule) would demonstrate direction and control by the client. It is even more frustrating because the other project is quite well developed and I enjoy working on it, so I would rather actually do the work!
Instead all that has happened is I have upset the client by insisting that they draw up another contract, or a work schedule amendment, instead of just getting started on the high priority work. I am damaging my reputation by not getting started on work I would actually like to do, making absolutely terrible business decisions, just because of this stupid IR35 legislation.
I guess i'm just bellyaching, but I would appreciate some views on it, and perhaps any stories of similar experiences from other contractors.
Cheers
Jon
Had an interesting experience with a client yesterday. I have a 3 month contract with them, which has started to roll over because the work is far more extensive than what could be completed in time, so i'm in the 4th month of it at the moment, and they are quite happy with that.
I get an email from the Project Manager telling me to stop work on my current project for a couple of days to add some high priority features to a different project. This other project is a project I developed for them last year, but that contract has long ended, and my current work schedule only describes work on my current project.
The problem is I had to refuse to do this other work, as them telling me what to work on and when (especially outside of the work schedule) would demonstrate direction and control by the client. It is even more frustrating because the other project is quite well developed and I enjoy working on it, so I would rather actually do the work!
Instead all that has happened is I have upset the client by insisting that they draw up another contract, or a work schedule amendment, instead of just getting started on the high priority work. I am damaging my reputation by not getting started on work I would actually like to do, making absolutely terrible business decisions, just because of this stupid IR35 legislation.
I guess i'm just bellyaching, but I would appreciate some views on it, and perhaps any stories of similar experiences from other contractors.
Cheers
Jon
Comment