• Visitors can check out the Forum FAQ by clicking this link. You have to register before you can post: click the REGISTER link above to proceed. To start viewing messages, select the forum that you want to visit from the selection below. View our Forum Privacy Policy.
  • Want to receive the latest contracting news and advice straight to your inbox? Sign up to the ContractorUK newsletter here. Every sign up will also be entered into a draw to WIN £100 Amazon vouchers!

Reply to: BOQ Prelims

Collapse

You are not logged in or you do not have permission to access this page. This could be due to one of several reasons:

  • You are not logged in. If you are already registered, fill in the form below to log in, or follow the "Sign Up" link to register a new account.
  • You may not have sufficient privileges to access this page. Are you trying to edit someone else's post, access administrative features or some other privileged system?
  • If you are trying to post, the administrator may have disabled your account, or it may be awaiting activation.

Previously on "BOQ Prelims"

Collapse

  • ChangePM
    replied
    Your prelims should cover everything from the admin involved in mobilising (RAMS etc) to the actual site-set up. Site office/cabin delivery and erection, welfare facilities, power and data.

    It's probably easier for you to make an itemised list of everything that you need to do to be in a position to work on the first day, then put a price next to each task.

    Leave a comment:


  • Jings
    replied
    Hi there, yes Prelims are those items not directly connected to the quantity of work provided.

    For example, site cabins, generator, fencing etc. Also overheads like the project manager and office support such as the buyers, planners etc.

    Many smaller companies include all these preliminary items simply by adding a factor onto their base costs, but a Prelims section in the BOQ enables you to break things out separately if you wish to do so, or if the client wishes to see it. You don't have to price preliminaries if your costs are included elsewhere - just say "included elsewhere".

    Leave a comment:


  • DaveB
    replied
    As Cojak said, this is primarily an IT contractors forum although we have a few stragglers from the trades as well.

    Anyone seen HaloJones recently?

    Anyway, a quick google found this

    https://www.designingbuildings.co.uk...n_construction

    And from that I'm guessing prelims are costs for anything that aren't part of the contract delivery itself but which are required in order to carry out the work. So site preparation, surreys etc.

    NBS suggest that 'the purpose of preliminaries is to describe the works as a whole, and to specify general conditions and requirements for their execution, including such things as subcontracting, approvals, testing and completion.' Preliminaries and work sections together describe what is required to complete the works required by the contract.

    Leave a comment:


  • greenlake
    replied
    Originally posted by Carp View Post
    Looking through bill of quantities the last item is "prelims". Could you help me understand what should be included in this?
    A quick google for bills of quantities brought me to this definition and list of items that may be included in the preliminaries section.

    Hope this helps.

    Leave a comment:


  • cojak
    replied
    Hi Carp,

    This isn’t a construction contractor’s forum, it’s an IT contractor’s forum.

    But someone here might be able to answer your question.

    Leave a comment:


  • Carp
    started a topic BOQ Prelims

    BOQ Prelims

    Hello guys.

    I run a small carpentry contracting business and recently got invited to tender for project consisting of 24 residential units.

    Looking through bill of quantities the last item is "prelims". Could you help me understand what should be included in this? Preparation of method statements and other paperwork? Will main contractor expect me to carry out works like temporary door installation etc. for my given price?

    Thanks.