Your prelims should cover everything from the admin involved in mobilising (RAMS etc) to the actual site-set up. Site office/cabin delivery and erection, welfare facilities, power and data.
It's probably easier for you to make an itemised list of everything that you need to do to be in a position to work on the first day, then put a price next to each task.
- Visitors can check out the Forum FAQ by clicking this link. You have to register before you can post: click the REGISTER link above to proceed. To start viewing messages, select the forum that you want to visit from the selection below. View our Forum Privacy Policy.
- Want to receive the latest contracting news and advice straight to your inbox? Sign up to the ContractorUK newsletter here. Every sign up will also be entered into a draw to WIN £100 Amazon vouchers!
Reply to: BOQ Prelims
Collapse
You are not logged in or you do not have permission to access this page. This could be due to one of several reasons:
- You are not logged in. If you are already registered, fill in the form below to log in, or follow the "Sign Up" link to register a new account.
- You may not have sufficient privileges to access this page. Are you trying to edit someone else's post, access administrative features or some other privileged system?
- If you are trying to post, the administrator may have disabled your account, or it may be awaiting activation.
Logging in...
Previously on "BOQ Prelims"
Collapse
-
Hi there, yes Prelims are those items not directly connected to the quantity of work provided.
For example, site cabins, generator, fencing etc. Also overheads like the project manager and office support such as the buyers, planners etc.
Many smaller companies include all these preliminary items simply by adding a factor onto their base costs, but a Prelims section in the BOQ enables you to break things out separately if you wish to do so, or if the client wishes to see it. You don't have to price preliminaries if your costs are included elsewhere - just say "included elsewhere".
Leave a comment:
-
As Cojak said, this is primarily an IT contractors forum although we have a few stragglers from the trades as well.
Anyone seen HaloJones recently?
Anyway, a quick google found this
https://www.designingbuildings.co.uk...n_construction
And from that I'm guessing prelims are costs for anything that aren't part of the contract delivery itself but which are required in order to carry out the work. So site preparation, surreys etc.
NBS suggest that 'the purpose of preliminaries is to describe the works as a whole, and to specify general conditions and requirements for their execution, including such things as subcontracting, approvals, testing and completion.' Preliminaries and work sections together describe what is required to complete the works required by the contract.
Leave a comment:
-
A quick google for bills of quantities brought me to this definition and list of items that may be included in the preliminaries section.Originally posted by Carp View PostLooking through bill of quantities the last item is "prelims". Could you help me understand what should be included in this?
Hope this helps.
Leave a comment:
-
Hi Carp,
This isn’t a construction contractor’s forum, it’s an IT contractor’s forum.
But someone here might be able to answer your question.
Leave a comment:
-
BOQ Prelims
Hello guys.
I run a small carpentry contracting business and recently got invited to tender for project consisting of 24 residential units.
Looking through bill of quantities the last item is "prelims". Could you help me understand what should be included in this? Preparation of method statements and other paperwork? Will main contractor expect me to carry out works like temporary door installation etc. for my given price?
Thanks.Tags: None
- Home
- News & Features
- First Timers
- IR35 / S660 / BN66
- Employee Benefit Trusts
- Agency Workers Regulations
- MSC Legislation
- Limited Companies
- Dividends
- Umbrella Company
- VAT / Flat Rate VAT
- Job News & Guides
- Money News & Guides
- Guide to Contracts
- Successful Contracting
- Contracting Overseas
- Contractor Calculators
- MVL
- Contractor Expenses
Advertisers
Contractor Services
CUK News
- Umbrella, PEO/GPP, or salaried EOR. Which is up 153% in 2026? Yesterday 08:43
- Outside IR35 isn’t making a comeback in 2026/27 — it’s something more complex Aug 5 04:55
- Why contractors keep putting off their pension (and why I'm one of them) Aug 4 02:43
- HMRC loan charge settlement offer: 3 things to check before you sign Aug 3 07:41
- HMRC standstill agreements extended to 72 months: why the term's doubled, and what to check before signing Jul 31 05:53
- Who owns the loans? Inside the mystery of the loan charge recall scandal Jul 30 06:20
- Umbrella company winding-up petitions in 2026: the practical guide for contractors Jul 29 05:29
- Payments on Account deadline: what contractors must do before July 31st — maybe for the final few times Jul 28 08:01
- Andy Burnham's first 100 days: five things contractors need from the new PM Jul 27 00:53
- Starmer vs Burnham on housing: What their rival plans mean for your contractor mortgage Jul 22 00:59

Leave a comment: