Thanks very much for the advice - all your comments were really useful and helped me to stand my ground.
I spoke to the agency to hear their standard answer that everyone else is fine with it. It was easier to handle them because I knew I was not being unreasonable (thanks for assuring me guys!). And Qdos backed me up - best £ I ever spent!
I prepared a schedule based on IPSE's schedule template, 'job' description, and what I was told at the interview. I included a clause about spending first week gathering client's requirements. Also I said that schedule may be amended if mutually agreed by my LTD and the client after the first week. I also included specific deliverables.
Agency agreed with every detail
It might not be ideal but I definitely feel much better about it now. Happy to have the contract sorted after all
- Visitors can check out the Forum FAQ by clicking this link. You have to register before you can post: click the REGISTER link above to proceed. To start viewing messages, select the forum that you want to visit from the selection below. View our Forum Privacy Policy.
- Want to receive the latest contracting news and advice straight to your inbox? Sign up to the ContractorUK newsletter here. Every sign up will also be entered into a draw to WIN £100 Amazon vouchers!
Reply to: How explicit schedule should be?
Collapse
You are not logged in or you do not have permission to access this page. This could be due to one of several reasons:
- You are not logged in. If you are already registered, fill in the form below to log in, or follow the "Sign Up" link to register a new account.
- You may not have sufficient privileges to access this page. Are you trying to edit someone else's post, access administrative features or some other privileged system?
- If you are trying to post, the administrator may have disabled your account, or it may be awaiting activation.
Logging in...
Previously on "How explicit schedule should be?"
Collapse
-
Originally posted by Jessica@WhiteFieldTax View PostTo answer original question, as detailed as possible. If its a struggle, start be codifying the key performance variables, the things mentioned at interview, the things that if you didn't do could lead to termination, etc.
Leave a comment:
-
To answer original question, as detailed as possible. If its a struggle, start be codifying the key performance variables, the things mentioned at interview, the things that if you didn't do could lead to termination, etc.
Leave a comment:
-
Originally posted by expat View PostAnd BTW as I think you have guessed, agents always say "but everybody else is OK with it".
Leave a comment:
-
Originally posted by FK1 View PostThe idea is to follow B2B practice and make two independent contracts. It might be in a form of separate schedules if each of them constitute a new contract. One for their needs analysis and another for work itself.
The first contract (a few days) is like a normal stage for requirements gathering, meetings and then actual contract negotiations. In the very real B2B it is normal to do that for free and definitely with no obligation whatsoever to offer/accept.
It might benefit you as you will commit yourself not so blindly. You might be simply not happy with your certain duties or working conditions.
P.S. But you have to balance between "the proper" thing and "realistic" one. It is your first contract and it might be very important for you. Try to argue politely and negotiate gently.
At least an employee does not negotiate a contract's terms Good luck!
I very much want and intend to keep it B2B, but also realise that not everything I read will be applicable in real life.
Lets hope I won't mess it up
Leave a comment:
-
Originally posted by squirrel99 View PostThanks
Do you mean to ask for a draft schedule to be included in contract, and then detailed schedule to be signed off within a week from starting the work?
The first contract (a few days) is like a normal stage for requirements gathering, meetings and then actual contract negotiations. In the very real B2B it is normal to do that for free and definitely with no obligation whatsoever to offer/accept.
It might benefit you as you will commit yourself not so blindly. You might be simply not happy with your certain duties or working conditions.
P.S. But you have to balance between "the proper" thing and "realistic" one. It is your first contract and it might be very important for you. Try to argue politely and negotiate gently.
At least an employee does not negotiate a contract's terms Good luck!
Leave a comment:
-
Originally posted by FK1 View PostI wouldn't. I would ask for two agreements. The first for one week to determine a client's needs and then the second as normal one. It would be then reflect B2B much better.
Do you mean to ask for a draft schedule to be included in contract, and then detailed schedule to be signed off within a week from starting the work?
Leave a comment:
-
Originally posted by squirrel99 View PostI did quite a bit of reading, but this is still unclear - hopefully it's ok to ask
How does schedule normally look like? My contract doesn't include any deliverables, only says:
The provision of specialist services as Programme Administrator. The contract provides that the services will be defined within 48 hours of the start of the agreement between the company and the hirer.
Would you accept this?
Qdos says the contract is outside IR35, but suggests to ask for a schedule of actual deliverables before signing the contract.
Leave a comment:
-
Originally posted by expat View PostAnd BTW as I think you have guessed, agents always say "but everybody else is OK with it".
Leave a comment:
-
And BTW as I think you have guessed, agents always say "but everybody else is OK with it".
Leave a comment:
-
Originally posted by northernladuk View PostThe contract might be out side IR35 but your working practices will trump that ultimately. You go in to a situation where D&C is almost a given the regardless of how tight you contract is you are stuffed.
Leave a comment:
-
The contract might be out side IR35 but your working practices will trump that ultimately. You go in to a situation where D&C is almost a given the regardless of how tight you contract is you are stuffed.
Leave a comment:
-
Thanks for reply
I was confused as Qdos said I am outside IR35. Only when I called them to ask about this clause specifically they said 'well it would be better if you get the schedule now'.
So I will try to get the schedule before signing the contract, but I wanted to make sure I am being reasonable before calling my agency (again) tomorrow morning. They know it's my first contract and their answer to my requests is 'believe me - all consultants do it this way.'
I didn't look at it as a control thing considering that it's a part of the contract - to agree the deliverables at the beginning of the contract. Would it be a good idea to remove this clause then?
Leave a comment:
-
So as soon as you start they will exercise direction and Control over you? That's truly awful.
QDOS are experts in their field. If they say get one why are you asking us?
Leave a comment:
-
How explicit schedule should be?
I did quite a bit of reading, but this is still unclear - hopefully it's ok to ask
How does schedule normally look like? My contract doesn't include any deliverables, only says:
The provision of specialist services as Programme Administrator. The contract provides that the services will be defined within 48 hours of the start of the agreement between the company and the hirer.
Would you accept this?
Qdos says the contract is outside IR35, but suggests to ask for a schedule of actual deliverables before signing the contract.Tags: None
- Home
- News & Features
- First Timers
- IR35 / S660 / BN66
- Employee Benefit Trusts
- Agency Workers Regulations
- MSC Legislation
- Limited Companies
- Dividends
- Umbrella Company
- VAT / Flat Rate VAT
- Job News & Guides
- Money News & Guides
- Guide to Contracts
- Successful Contracting
- Contracting Overseas
- Contractor Calculators
- MVL
- Contractor Expenses
Advertisers
Contractor Services
CUK News
- Labour’s plan to regulate umbrella companies: a closer look Yesterday 09:24
- When HMRC misses an FTT deadline but still wins another CJRS case Nov 20 09:20
- How 15% employer NICs will sting the umbrella company market Nov 19 09:16
- Contracting Awards 2024 hails 19 firms as best of the best Nov 18 09:13
- How to answer at interview, ‘What’s your greatest weakness?’ Nov 14 09:59
- Business Asset Disposal Relief changes in April 2025: Q&A Nov 13 09:37
- How debt transfer rules will hit umbrella companies in 2026 Nov 12 09:28
- IT contractor demand floundering despite Autumn Budget 2024 Nov 11 09:30
- An IR35 bill of £19m for National Resources Wales may be just the tip of its iceberg Nov 7 09:20
- Micro-entity accounts: Overview, and how to file with HMRC Nov 6 09:27
Leave a comment: