Reporting project slippage

Collapse
X
  •  
  • Filter
  • Time
  • Show
Clear All
new posts

    Reporting project slippage

    In the past I have reported project slippage, announced delays, risks, issues etc. No one likes this news and it's better not to be the messenger if you can help it.

    Lately the phrase that seems in common parlance is "moved to the right"

    Example :

    As the business changed the requirements we needed to conduct an impact analysis. As a result of this the deliverable is much larger and hence the project plan has "moved to the right"
    Doesn't seem to evoke the same emotions as "the project has slipped"
    Knock first as I might be balancing my chakras.

    #2
    "Deadline passed without event or alarm"
    And what exactly is wrong with an "ad hominem" argument? Dodgy Agent, 16-5-2014

    Comment


      #3
      Originally posted by suityou01 View Post
      In the past I have reported project slippage, announced delays, risks, issues etc. No one likes this news and it's better not to be the messenger if you can help it.

      Lately the phrase that seems in common parlance is "moved to the right"

      Example :



      Doesn't seem to evoke the same emotions as "the project has slipped"
      It's not new - I've worked extensively on the NHS National Programme for IT and there's been plenty of this. 'Moves to the right' does make it sound like you're going to deport all non-Aryan project team members.

      Comment


        #4
        Originally posted by suityou01 View Post
        In the past I have reported project slippage, announced delays, risks, issues etc. No one likes this news and it's better not to be the messenger if you can help it.

        Lately the phrase that seems in common parlance is "moved to the right"

        Example :



        Doesn't seem to evoke the same emotions as "the project has slipped"
        That wouldn't fly here.

        When I report slippage I get 2 questions:

        1) Who is to blame?
        2) What are you going to do to fix it?

        Comment


          #5
          Originally posted by oracleslave View Post
          That wouldn't fly here.

          When I report slippage I get 2 questions:

          1) Who is to blame?
          2) What are you going to do to fix it?
          1) Somebody who's just left
          2) Send you an invoice
          And what exactly is wrong with an "ad hominem" argument? Dodgy Agent, 16-5-2014

          Comment


            #6
            Originally posted by suityou01 View Post
            In the past I have reported project slippage, announced delays, risks, issues etc. No one likes this news and it's better not to be the messenger if you can help it.

            Lately the phrase that seems in common parlance is "moved to the right"

            Example :

            As the business changed the requirements we needed to conduct an impact analysis. As a result of this the deliverable is much larger and hence the project plan has "moved to the right"
            Doesn't seem to evoke the same emotions as "the project has slipped"
            In your example, the project hasn't slipped. Requirements have changed.

            Hth.

            My suggestion would be for you to find a job that you can do.

            Comment


              #7
              Originally posted by oracleslave View Post
              That wouldn't fly here.

              When I report slippage I get 2 questions:

              1) Who is to blame?
              2) What are you going to do to fix it?
              1) In the example above the slippage was caused by a change in requirements
              2) Reprioritise the requirements and deliver the remainder in a later phase.
              Knock first as I might be balancing my chakras.

              Comment


                #8
                Originally posted by SupremeSpod View Post
                In your example, the project hasn't slipped. Requirements have changed.

                Hth.

                My suggestion would be for you to find a job that you can do.
                1) You're a crap troll
                2) You look stupid for not understanding that a change in requirements could introduce slippage.
                Knock first as I might be balancing my chakras.

                Comment


                  #9
                  Originally posted by Mich the Tester View Post
                  1) Somebody who's just left
                  2) Send you an invoice
                  That answer will see you revert to your point 1) above sharpish.

                  Comment


                    #10
                    Originally posted by oracleslave View Post
                    That answer will see you revert to your point 1) above sharpish.
                    Fine, if it's such a tulipty clientco I'll go.
                    And what exactly is wrong with an "ad hominem" argument? Dodgy Agent, 16-5-2014