Originally posted by woohoo
View Post
Is your chap doing it all, tiling, plumbing & electrics may be done by others on day rates
But as a summary & not having seen the area:
Day 1: clear area & set out, minor BWIC such as core drill for pipe work
Day 2: install drainage & pipework
Day 2: form framing & install shower tray & connect
Day 3: Tiling
Day 4: Tiling
Day 5: install & connect pump
Day 6: grouting of tiles
Day 7: Make good T&C
Day 8: Float / unforeseen