Hinkley Point: EDF adds £1.5bn to nuclear plant cost
But don't worry nothing to do with Brexit and everything to do with a government who cannot plan long term or make decisions. Construction of the third runway at Heathrow will begin after Dubai runs out of building plots.
But don't worry nothing to do with Brexit and everything to do with a government who cannot plan long term or make decisions. Construction of the third runway at Heathrow will begin after Dubai runs out of building plots.
French energy supplier EDF has estimated that the cost of completing the new Hinkley Point nuclear plant will be nearly 10% more than expected.
The company, which is the project's main backer, said the total cost of the power station was likely to rise by £1.5bn to £19.6bn.
Hinkley Point C would be the UK's first new nuclear plant for decades, but has been beset with budget problems.
An EDF review found the project could also be delayed by up to 15 months.
However, the firm said it still hoped to finish the first nuclear reactor by the end of 2025 as planned.
The extra costs partly result from adapting the project's design to meet the demands of UK regulators, the company said.
Climate campaigners said Hinkley Point was "over time and over budget" only nine months since being approved.
Hinkley Point deal 'risky and expensive'
What is Hinkley Point and why is it important?
EDF is building two new reactors at Hinkley Point, which are expected to provide 7% of the country's electricity needs for 60 years.
France's state-controlled energy firm is funding two-thirds of the project, with China investing the rest.
A government spokeswoman said "the cost of construction, including any overruns, sits with the contractor".
"Consumers won't pay a penny until Hinkley is built; it will provide clean, reliable electricity powering six million homes," she said.
The company, which is the project's main backer, said the total cost of the power station was likely to rise by £1.5bn to £19.6bn.
Hinkley Point C would be the UK's first new nuclear plant for decades, but has been beset with budget problems.
An EDF review found the project could also be delayed by up to 15 months.
However, the firm said it still hoped to finish the first nuclear reactor by the end of 2025 as planned.
The extra costs partly result from adapting the project's design to meet the demands of UK regulators, the company said.
Climate campaigners said Hinkley Point was "over time and over budget" only nine months since being approved.
Hinkley Point deal 'risky and expensive'
What is Hinkley Point and why is it important?
EDF is building two new reactors at Hinkley Point, which are expected to provide 7% of the country's electricity needs for 60 years.
France's state-controlled energy firm is funding two-thirds of the project, with China investing the rest.
A government spokeswoman said "the cost of construction, including any overruns, sits with the contractor".
"Consumers won't pay a penny until Hinkley is built; it will provide clean, reliable electricity powering six million homes," she said.
Comment