Hi all,
I was looking for an opinion on some wording within an outside IR35 contract. Under a section called `competence`it states the following:
The contractor services will therefore be monitored continuously to ensure that competence to the requisite quality and quantity required by Agency X and Agency X's client is achieved within the required timescales (which will typically be in 2 weeks or 4 weeks of the start date); and once (and if) initial competence is demonstrated it is maintained for the duration of the term of the assignment.
In the event that Agent X or Agent X's client believes that you or the contractor have failed to maintain the level of competence required under clause 4/1 then Agent X shall be entitled at any time at its absolute discretion (and without further liability to you) to terminate the contractor services. In the event of early termination of the contractor Services during the intitial term under this clause 4.2 Agent X shall be entitled to deduct from monies owed to you up to 10 days of Day Rate as set out under clause 10.
I have been contracting for 8 years now and I have never known for an agency to deduct monies up to 10 days if the client decides to terminate. So essentially I won't be be able to bill even though I work 10 days and the client decides they aren't happy and wish to terminate. This can't be normal...is it? If I work a day I expect to bill for that day. The shoddy agents that I have been liaising with have dodged me for weeks after saying its a quick start and now its been one month one and they send me out this contract on a Friday the weekend before I am supposed to start. I also have no time to get an IR35 review and I'm left not feeling to comfortable or happy with some of this wording. I feel nervous that I could start the role and work for 10 days, client may or may not terminate in 12 days and I can only invoice for 2 days because the agency will take 10 days worth of day rate. Something doesn't add up or seem right.
Please advise!
I was looking for an opinion on some wording within an outside IR35 contract. Under a section called `competence`it states the following:
The contractor services will therefore be monitored continuously to ensure that competence to the requisite quality and quantity required by Agency X and Agency X's client is achieved within the required timescales (which will typically be in 2 weeks or 4 weeks of the start date); and once (and if) initial competence is demonstrated it is maintained for the duration of the term of the assignment.
In the event that Agent X or Agent X's client believes that you or the contractor have failed to maintain the level of competence required under clause 4/1 then Agent X shall be entitled at any time at its absolute discretion (and without further liability to you) to terminate the contractor services. In the event of early termination of the contractor Services during the intitial term under this clause 4.2 Agent X shall be entitled to deduct from monies owed to you up to 10 days of Day Rate as set out under clause 10.
I have been contracting for 8 years now and I have never known for an agency to deduct monies up to 10 days if the client decides to terminate. So essentially I won't be be able to bill even though I work 10 days and the client decides they aren't happy and wish to terminate. This can't be normal...is it? If I work a day I expect to bill for that day. The shoddy agents that I have been liaising with have dodged me for weeks after saying its a quick start and now its been one month one and they send me out this contract on a Friday the weekend before I am supposed to start. I also have no time to get an IR35 review and I'm left not feeling to comfortable or happy with some of this wording. I feel nervous that I could start the role and work for 10 days, client may or may not terminate in 12 days and I can only invoice for 2 days because the agency will take 10 days worth of day rate. Something doesn't add up or seem right.
Please advise!
Comment