I'm a newbie contractor and been doing at it for only four months. I'm directly contracting with the client and no agency is involved. My job currently involves clearing a backlog of bugs, nothing too exciting there! The company I'm working for is in the same sector that I have worked in for over a decade - so have a lot of experience with their client base as well as the type of application that's being developed.
After getting my head around their application, I proposed some enhancements and demoed my ideas to the director/architect and other senior developers on the team. The director loved the ideas and has shown a keen interest in implementing the work. We’ve had a chat and I estimated the work to take around eight months. My initial thoughts were when I simply renewal my contract at the beginning of April, we would renegotiate and simply carry on from there!
However, and completely understandably, the director wants me write up a simple spec with a timeline and estimated costs for the work. So simple put I wouldn’t be on a day rate anymore but bill for a whole project.
I’m a little unsure with exactly how I would proceed with this! Being only a recent contractor I’m now currently being asked to spec up the work and come up with a cost! A simple formula would be to charge my day rate for the 8 months + plus 20%. That sounds reasonable as if the work takes longer I would obviously only get paid for my original estimate.
I know I probably sound very naïve here! But not sure where to start or where go to with getting more info! The director is sympathetic and is guiding me through the process, we have developed a good working relationship. I of course need to get as much impartial information as possible but just don’t know where to being, not having an agent and my accountant couldn’t advise me at all… hoping someone on here can point me in the right direction!
Many Thanks
DS
P.S. Thanks for all the contributors on here, made my transition into contracting so much easier!
After getting my head around their application, I proposed some enhancements and demoed my ideas to the director/architect and other senior developers on the team. The director loved the ideas and has shown a keen interest in implementing the work. We’ve had a chat and I estimated the work to take around eight months. My initial thoughts were when I simply renewal my contract at the beginning of April, we would renegotiate and simply carry on from there!
However, and completely understandably, the director wants me write up a simple spec with a timeline and estimated costs for the work. So simple put I wouldn’t be on a day rate anymore but bill for a whole project.
I’m a little unsure with exactly how I would proceed with this! Being only a recent contractor I’m now currently being asked to spec up the work and come up with a cost! A simple formula would be to charge my day rate for the 8 months + plus 20%. That sounds reasonable as if the work takes longer I would obviously only get paid for my original estimate.
I know I probably sound very naïve here! But not sure where to start or where go to with getting more info! The director is sympathetic and is guiding me through the process, we have developed a good working relationship. I of course need to get as much impartial information as possible but just don’t know where to being, not having an agent and my accountant couldn’t advise me at all… hoping someone on here can point me in the right direction!
Many Thanks
DS
P.S. Thanks for all the contributors on here, made my transition into contracting so much easier!
Comment