Hi,
Could anyone provide insight to the following situation?
A signed contract (between end client, agency and accepted via brolly by contractor) states that in addition to a daily rate of pay, overtime at a specified rate will be paid.
However, the original job offer cites clearly just a daily rate.
The contractor, on receipt of his first payment, then notifies the company for whom he is working that an overtime payment was not the original intention of the poorly drawn contract.
1. Is the contractor liable to refund the overtime sum?
In this case the contractor was asked to extend his period of work by one week and several weeks later heard that he was not being paid for this week to offset the earlier overpayment.
As this action alone was not enough to clear the overpayment the remaining balance overpaid is now being claimed by the brolly although the contract has finished.
2. Is the contractor liable to repay this balancing sum?
Thanks,
XyNm777
Could anyone provide insight to the following situation?
A signed contract (between end client, agency and accepted via brolly by contractor) states that in addition to a daily rate of pay, overtime at a specified rate will be paid.
However, the original job offer cites clearly just a daily rate.
The contractor, on receipt of his first payment, then notifies the company for whom he is working that an overtime payment was not the original intention of the poorly drawn contract.
1. Is the contractor liable to refund the overtime sum?
In this case the contractor was asked to extend his period of work by one week and several weeks later heard that he was not being paid for this week to offset the earlier overpayment.
As this action alone was not enough to clear the overpayment the remaining balance overpaid is now being claimed by the brolly although the contract has finished.
2. Is the contractor liable to repay this balancing sum?
Thanks,
XyNm777
Comment