Good morning,
I have just found this forum and apologise but as usual on a forum I am after a small amount of advice.
I currently run my own limited company and contract as I am sure most of us do and I am currently in a year long contract but it is the second year for the same company.
The issue I have is the work load is now excessive and to some degrees the contract has been breached as I am employed for a project but I have verbally agreed to assist on another than was in trouble based on the fact I was advised this would not take much time. Fast forward 6 weeks and this is so untrue it's unreal.
In the mean time I have been contacted about a new role via a friend and this new role is the next level up in terms of management so I am keen to accept for personnel progression.
I could obviously break contract based on breach of contract in my opinion but this is not what I want to do and also the contract has a termination agreement which I can activate anyway.
The question I have is the terminate clause says either party can terminate based on giving the notice period stated in the schedule but in reading the schedule there is no period stated (believe me I have checked a lot) I am guessing based on this I could give just a week although I don't believe that is appropriate as if I do between 4 and 6 weeks if will take the project to a more acceptable hand over point for my client, and although they are not going to be happy I want to ensure it is as painless for them as possible.
Does anyone see any issues in me giving 4-6 weeks notice based on the fact the schedule does not state a duration? Or am I intact being over generous in reality?
Thanks
Lee
I have just found this forum and apologise but as usual on a forum I am after a small amount of advice.
I currently run my own limited company and contract as I am sure most of us do and I am currently in a year long contract but it is the second year for the same company.
The issue I have is the work load is now excessive and to some degrees the contract has been breached as I am employed for a project but I have verbally agreed to assist on another than was in trouble based on the fact I was advised this would not take much time. Fast forward 6 weeks and this is so untrue it's unreal.
In the mean time I have been contacted about a new role via a friend and this new role is the next level up in terms of management so I am keen to accept for personnel progression.
I could obviously break contract based on breach of contract in my opinion but this is not what I want to do and also the contract has a termination agreement which I can activate anyway.
The question I have is the terminate clause says either party can terminate based on giving the notice period stated in the schedule but in reading the schedule there is no period stated (believe me I have checked a lot) I am guessing based on this I could give just a week although I don't believe that is appropriate as if I do between 4 and 6 weeks if will take the project to a more acceptable hand over point for my client, and although they are not going to be happy I want to ensure it is as painless for them as possible.
Does anyone see any issues in me giving 4-6 weeks notice based on the fact the schedule does not state a duration? Or am I intact being over generous in reality?
Thanks
Lee
Comment