Would appreciate some advice.
My current 6-month contract was originally due to end on 21st December. However, the project on which I'm working was recently cancelled, and so the agency gave me 4 weeks notice (as per my contract with them) on 17th November, so my last day was brought forward to 15th December.
The client now says they want me out on 13th (don't know why, it's the same for the other contractors in the team), so there will be 2 days when I should be working here, but will not be able to. That's about £600 gross on my current rate.
As I don't have another contract to go to, I need that money, so how do I go about getting it? Is the agent obliged to pay for the 2 days work, even though it was never carried out? How do I go about getting the money?
My current 6-month contract was originally due to end on 21st December. However, the project on which I'm working was recently cancelled, and so the agency gave me 4 weeks notice (as per my contract with them) on 17th November, so my last day was brought forward to 15th December.
The client now says they want me out on 13th (don't know why, it's the same for the other contractors in the team), so there will be 2 days when I should be working here, but will not be able to. That's about £600 gross on my current rate.
As I don't have another contract to go to, I need that money, so how do I go about getting it? Is the agent obliged to pay for the 2 days work, even though it was never carried out? How do I go about getting the money?
Comment