Contract options for consultancy work
Collapse
X
-
Yep, that's pretty much fixed price.The greatest trick the devil ever pulled was convincing the world that he didn't exist -
Yes, I think I'm coming round to this now! I was probably being lazy and didn't want to create a schedule for each deliverable. I'll get a SOW for each deliverable so can just raise a schedule for each one and send it over.Originally posted by fidot View PostAn over-arching contract with a schedule for each piece of work is the right way forward.
Just to clarify - I'll be directly engaged by one client only (the supplier), and the deliverable will be for their clients. I'll only have a contract/schedule with the one client though.
The number of days delivered will average out at 2 per week, but it may be higher or lower depending on the current deliverable requirement and also other, unrelated work I have on the go.
Cheers.Comment
-
Hmmmmm, is it fixed price, really?Originally posted by LondonManc View PostYep, that's pretty much fixed price.
Most would be charging just a price with contingency time built in.
If you came in under or managed to do it quicker - happy days.
Obviously, difficult to do when you have other parties delivering to you to make your part happen.
The contract has to be watertight for fixed price.The Chunt of Chunts.Comment
-
I'd agree with the comments about the schedule but something doesn't sound right....
The schedule would have to be upfront and be part of the contract no? I get the impression the OP doesn't know and it's talking about writing up a schedule as and when the work get's agreed. He's not going to know every piece of work when it's a contract with no end date.
All that leads to my assumption he's just moving on to the next bit of work he is asked for. If he then writes up a schedule there and then he's just creating a paper trail that doesn't reflect the overarching contract. If it was as easy as that to document every piece of work the client asks us then D&C would never be a problem.
If the OP has a project plan with all these on then yes happy days. I can't see he has that in this thread though.
What is different to the OP's situation and a BoS disguised permie that just moves between clients when he is told?
Now if he could bring in a second person to speed the work up or sub it out then happy days!!!Last edited by northernladuk; 25 January 2017, 16:48.'CUK forum personality of 2011 - Winner - Yes really!!!!
Comment
-
I'm paying for ten days for you to do something. If it takes you 8 good luck. If it takes you 15, tough. Should bill a day or two for analysis for that sort of thing though, so that you don't get stung.Originally posted by MrMarkyMark View PostHmmmmm, is it fixed price, really?
Most would be charging just a price with contingency time built in.
If you came in under or managed to do it quicker - happy days.
Obviously, difficult to do when you have other parties delivering to you to make your part happen.
The contract has to be watertight for fixed price.The greatest trick the devil ever pulled was convincing the world that he didn't existComment
-
Contract options for consultancy work
No project plan to start with is available as it is as and when services are needed. So the supplier sells product & pro services to a new client, and I'm then engaged to deliver the PS work. No idea who's going to be buying stuff in 6 months time.Originally posted by northernladuk View PostIf the OP has a project plan with all these on then yes happy days. I can't see he has that in this thread though.
Maybe because I'll be offered an engagement and I can decide whether to take or leave it, depending on my current workload???Originally posted by northernladuk View PostWhat is different to the OP's situation and a BoS disguised permie that just moves between clients when he is told?
This was something I bought up at the initial discussion, but for now it'll just be me. It depends on how the work ramps up over time as to when more resource is required.Originally posted by northernladuk View PostNow if he could bring in a second person to speed the work up or sub it out then happy days!!!
It's possible I could sub some work out though.Comment
- Home
- News & Features
- First Timers
- IR35 / S660 / BN66
- Employee Benefit Trusts
- Agency Workers Regulations
- MSC Legislation
- Limited Companies
- Dividends
- Umbrella Company
- VAT / Flat Rate VAT
- Job News & Guides
- Money News & Guides
- Guide to Contracts
- Successful Contracting
- Contracting Overseas
- Contractor Calculators
- MVL
- Contractor Expenses
Advertisers

Comment