Originally posted by BlasterBates
View Post
I've worked on Fixed Price before and although in theory that sounds fine (tests passed = implied acceptance = payment trigger), it usually ends up in a bunfight with the system integrator over how many tests and which ones are included in scope. If you can't define your deliverables up front, then accurately defining the tests to pass would be near impossible?
You're right though about scope creep, it makes change control even more important. Oh the fun we had arguing whether an issue was a defect or a CR, and the man hours we wasted doing so....