Hi, usual apologies if this is covered elsewhere - and sorry that this has turned into a long post
I work in a fairly niche market with plenty of different customers for short projects working direct, through agency or another consultancy. So I rush around with laptop, get statement of work for everything I do, quite a bit of financial risk in some of my work etc etc
but - most of the time the contract is quite undefined - eg work on project x for up to 20 days, dates and times to be agreed. I'll sit down with the client and plan the work and the days that I will be on site. They only pay for the days I use and if its looking like its going to take longer then I tell the client and they decide whether to order more work. All standard stuff and not MOO I guess
So I started work with a new customer a few months ago. The usual vague requirements. Agreed to deliver up to 60 days work. Obviously fixed dates cannot be worked out that far in advance as I still have to fit it around other clients, so we agreed to aim for 4 days a week (now 3). And so we started on pretty much the same basis as I would do with any customer.
So over the months its started to feel like I actually work there (even though part time). I've never really worried about IR35 before as I guess I've never even come close, but is it possible that this contract is drifting towards IR35 as they now want to buy some more days? I didn't start with that intention and my T&Cs are the same as for all my assignments (certainly not a sham in those cases)
Some facts
- HR requires I have a pass to get in building due to length of time I'm there
- practicallity requires I have my own desk, pc, login, email account
- was invited to the xmas party (didn't go because I was ill)
- I do decide which days I come in so that I can fit other work in - but usually try to fit around what this client needs
- I try to match working hours to not look like I'm skiving
- I get a constantly updated list of (quite detailed) requirements and priorities from the PM (does this count as control?)
- While waiting for other areas of the project to catch up I have done some work on other areas of the system (didn't hear the alarm bells)
Any thoughts please? I know I could pay for some advice but thought I'd try and get some for free
thanks
I work in a fairly niche market with plenty of different customers for short projects working direct, through agency or another consultancy. So I rush around with laptop, get statement of work for everything I do, quite a bit of financial risk in some of my work etc etc
but - most of the time the contract is quite undefined - eg work on project x for up to 20 days, dates and times to be agreed. I'll sit down with the client and plan the work and the days that I will be on site. They only pay for the days I use and if its looking like its going to take longer then I tell the client and they decide whether to order more work. All standard stuff and not MOO I guess
So I started work with a new customer a few months ago. The usual vague requirements. Agreed to deliver up to 60 days work. Obviously fixed dates cannot be worked out that far in advance as I still have to fit it around other clients, so we agreed to aim for 4 days a week (now 3). And so we started on pretty much the same basis as I would do with any customer.
So over the months its started to feel like I actually work there (even though part time). I've never really worried about IR35 before as I guess I've never even come close, but is it possible that this contract is drifting towards IR35 as they now want to buy some more days? I didn't start with that intention and my T&Cs are the same as for all my assignments (certainly not a sham in those cases)
Some facts
- HR requires I have a pass to get in building due to length of time I'm there
- practicallity requires I have my own desk, pc, login, email account
- was invited to the xmas party (didn't go because I was ill)
- I do decide which days I come in so that I can fit other work in - but usually try to fit around what this client needs
- I try to match working hours to not look like I'm skiving
- I get a constantly updated list of (quite detailed) requirements and priorities from the PM (does this count as control?)
- While waiting for other areas of the project to catch up I have done some work on other areas of the system (didn't hear the alarm bells)
Any thoughts please? I know I could pay for some advice but thought I'd try and get some for free
thanks
Comment