Hi, started a new contract last month.
The job agency are being very pushy around which umbrella company I use.
They have a PSL and have pushed one of these beyond belief.
Background.. I was told I had the job on a Monday PM and all the stops were pulled out by everyone
involved for me to start at the new place of work on the Wednesday AM.
Therefore, to speed things up, I pretty much had no choice but to go with one of the agency's Umbrellas on their PSL so the contracts could be drawn up.
I explained that I needed more time to investigate the Umbrellas and make a decision but that I would use theirs in order to get contracts drawn up and back in to work ASAP.
At this point they agreed that they would fully investigate and be willing to switch to an umbrella of my choosing over the coming weeks.
Further in to my contract I then explained that I would instead be setting up my own LTD company.
I have now done this 4weeks in and am about to request they setup the contract with my LTD company and pay me for the last 4/5weeks to the LTD company.
I have had an email from them stating that all back timesheets (I have not invoiced or submittted or had ANY timesheets authroised yet) must go through their PSL umbrella that I initially signed up with..
Is this allowed?? I have worked on other contracts and switched umbrella companies half way through due to better rates for example.
Help appreciated.
Thanks
Bob
The job agency are being very pushy around which umbrella company I use.
They have a PSL and have pushed one of these beyond belief.
Background.. I was told I had the job on a Monday PM and all the stops were pulled out by everyone
involved for me to start at the new place of work on the Wednesday AM.
Therefore, to speed things up, I pretty much had no choice but to go with one of the agency's Umbrellas on their PSL so the contracts could be drawn up.
I explained that I needed more time to investigate the Umbrellas and make a decision but that I would use theirs in order to get contracts drawn up and back in to work ASAP.
At this point they agreed that they would fully investigate and be willing to switch to an umbrella of my choosing over the coming weeks.
Further in to my contract I then explained that I would instead be setting up my own LTD company.
I have now done this 4weeks in and am about to request they setup the contract with my LTD company and pay me for the last 4/5weeks to the LTD company.
I have had an email from them stating that all back timesheets (I have not invoiced or submittted or had ANY timesheets authroised yet) must go through their PSL umbrella that I initially signed up with..
Is this allowed?? I have worked on other contracts and switched umbrella companies half way through due to better rates for example.
Help appreciated.
Thanks
Bob
Comment