A lesson from this is to confirm matters directly with the client. Do not rely on the agency. It's obvious, of course - any third party, especially those with their own agenda, cannot necessarily be relied upon, and so in matters of importance cannot be relied upon.
I emailed Hays today.
There was no reply.
I thought the discussion would be easier in email, so I waited until 4.30pm before phoning.
I phoned, and was put through to not the original member of staff who handled the case (who was on holiday for a week, and is now unwell), nor the second (who...
A very good question.
Since I have (again, in my inexperience) signed, any changes can come only with their agreement.
Googling indicates other contractors having been successful in asking for IR35-related changes to Hays contracts, so I have some hope - on the other hand, my dimming view of...
A very good question.
I asked Hays prior to signing if the contract was inside or outside of IR35.
I was informed it was outside.
I'm afraid in my inexperience I took their answer at face value. I do know better than this, but I have to think about it to catch myself making this type of...
I this morning attended the UCAS building and spoke to the project manager and the HR recruiter handling my contract.
There had not been at any time a completed and signed contract between UCAS and Hays.
Hays' assurance to me that all the paperwork was complete was incorrect.
I will now...
It could have been inadvertant. It might be the information arrived on the Thursday or even late on the Thursday and simply did not reach the agent before Friday.
Or it might have been the agency knew long beforehand and knowingly withheld the information from me.
I will know on Monday, as I...
I am not troubled by the loss. It is also true or almost certainty true Hays will not accept a responsibility for it, although I may be doing them a dis-service, since I have not yet spoken to them. It is only my expectation.
I do think it important to correctly understand events that occur...
Good moring, ladies and gents.
I accepted last Thursday a contract through the recruitment agency Hays. The client is UCAS, in Cheltenham. I completed all the paperwork with Hays the day after. The start date was set to be Monday the 22nd of January.
I was at the time in Santa Cruz de...