+ Reply to Thread
Posts 1 to 8 of 8
  1. #1

    Nervous Newbie


    Join Date
    Jul 2017
    Posts
    1
    Thanks (Given)
    0
    Thanks (Received)
    0
    Likes (Given)
    0
    Likes (Received)
    0

    Cool Help - Contract Cancellation Query

    Hi first time poster here

    Hope you can help. I was asked to propose for some work for a public sector organisation:
    - drew up & sent an outline
    - got an email confirming wish to progress
    - got an email confirming funding was in place
    - I sent Statement of Works & T&Cs which had an effective date of 23/06/17 although work was to start 1st Aug. Half payment due on 1st Aug & final Half upon delivery.
    - I was confirmed as consultant in 2x public forum meetings
    - after which I got further follow up emails asking me to liaise with individuals as part of the work/actions etc
    - scheduled my diary workload accordingly

    I went on hols for 2wks came back to an email saying no longer wish to progress.

    I have suggested I am contracted to them till end of Aug and offered my services for other work to avoid a breach of contract scenario - they are saying their legal teams view is that we are not in a contract. (Informal off record chat with 1 of them early doors on this gave me a diff opinion).

    Previously done consultancy work for this organisation & the steps outlined was what occurred (I.e. Set a precedent). I believe they approached a large organisation to do work, got messed around, so asked me to do it. Went back to original company (whose email query did they wish to progress I've seen) & they've demanded the work & me the little guy has been shafted.

    Any thoughts or advice I'm just a single consultant now after arranging work around them as a favour I will have no income for 8wks.

    Any advice appreciated

  2. #2

    I live on CUK

    SueEllen's Avatar
    Join Date
    Nov 2005
    Location
    in the Park
    Posts
    26,309
    Thanks (Given)
    1135
    Thanks (Received)
    934
    Likes (Given)
    4258
    Likes (Received)
    3769

    Default

    What penalty clause was in your contract of one of you withdrew early? If there wasn't one then you get SFA.
    "You’re just a bad memory who doesn’t know when to go away" JR

  3. #3

    Old Greg is my bitch's bitch

    northernladyuk's Avatar
    Join Date
    Nov 2011
    Location
    Working the streets of your imagination
    Posts
    6,100
    Thanks (Given)
    803
    Thanks (Received)
    390
    Likes (Given)
    312
    Likes (Received)
    1740

    Default

    Quote Originally Posted by SueEllen View Post
    What penalty clause was in your contract of one of you withdrew early? If there wasn't one then you get SFA.
    WSES. What does your signed contract say?
    Where there's muck there's brass.

  4. #4

    TripleIronDad

    BrilloPad's Avatar
    Join Date
    Aug 2006
    Posts
    95,043
    Thanks (Given)
    19409
    Thanks (Received)
    5059
    Likes (Given)
    19409
    Likes (Received)
    8831

    Default

    How long was your notice period? Not that it matters as there is no work for you to do.
    Katy Perry - don't be afraid to catch feels. Taylor Swift - feels $1 a go.

  5. #5

    Old Greg is my bitch's bitch

    northernladyuk's Avatar
    Join Date
    Nov 2011
    Location
    Working the streets of your imagination
    Posts
    6,100
    Thanks (Given)
    803
    Thanks (Received)
    390
    Likes (Given)
    312
    Likes (Received)
    1740

    Default

    Quote Originally Posted by BrilloPad View Post
    How long was your notice period? Not that it matters as there is no work for you to do.
    Depends on the contract. This is not typical contractor stuff.
    Where there's muck there's brass.

  6. #6

    Contractor Among Contractors

    Lance's Avatar
    Join Date
    Sep 2013
    Location
    home
    Posts
    1,147
    Thanks (Given)
    11
    Thanks (Received)
    47
    Likes (Given)
    117
    Likes (Received)
    247

    Default

    You need to carefully read the Ts and Cs. See what they tell you. If you think you have grounds then write them a formal letter. You could get laywered up now but that depends on your skill at Reading the Ts and Cs.
    See You Next Tuesday

  7. #7

    Faqqed Off

    TheFaQQer's Avatar
    Join Date
    Oct 2006
    Posts
    35,838
    Thanks (Given)
    369
    Thanks (Received)
    1233
    Likes (Given)
    3564
    Likes (Received)
    3087

    Default

    Quote Originally Posted by AliG999 View Post
    - I sent Statement of Works & T&Cs which had an effective date of 23/06/17 although work was to start 1st Aug. Half payment due on 1st Aug & final Half upon delivery.
    Go back to the T&Cs and see what they say about cancellation prior to work commencing. Were they accepted by the (prospective) client? If they were then you invoice for the amount owed and chase it when they don't pay up.
    Best Forum Advisor, 2014
    Work in the public sector? You can read my FAQ here
    Click here to get 15% off your first year's IPSE membership

  8. #8

    Still gathering requirements...


    Join Date
    Jul 2017
    Location
    London
    Posts
    38
    Thanks (Given)
    1
    Thanks (Received)
    3
    Likes (Given)
    2
    Likes (Received)
    2

    Default

    I suspect from original message that there is no signed contract here - there was a discussion about the work, the scope was discussed but the formal paperwork was going to be signed when he got back from hols at which point they did the dirty.

    Technically there could be a verbal contract here. There was certainly an offer made by the OP. There may be an argument about acceptance but the pattern of behaviour seems to suggest it was accepted (confirmed in a public forum, asked to liaise with the team etc). There fact that you did some pre-work in liaising with their team (at their behest) would seem to imply there was some consideration and the expectation was that there would be a binding arrangement.

    You have two choices here. Feel massively aggrieved and tell everyone what a bunch of **** these people are, but chalk it up to experience. Or try to get something out of it.

    If you go down the second route, I suggest writing to the hiring manager outlining that you consider that there was a verbal agreement that you would do the work, that this was confirmed through the public forums etc and that you had in good faith made plans to start today. Estimate what the "breach of contract" has cost you - after considering what you can do to mitigate the loss (eg if you can get a new contract in a couple of weeks, you can estimate that this has cost you two weeks of fees). Then explain this figure to them, and ask them to cover your loss. Then say that if they fail to pay you the amount in the next 7/14 days, you will start action against them in the Small Claims Court.

    If your claim is less than £5k, it will cost you £185 to start proceedings against them. If they file a defence, you then have to pay another £110 pre-hearing fee and £335 if it goes to court. You don't have to pay their costs even if you lose. So you are gambling £630 on your ability to convince a judge that there was a verbal contract and they screwed you over.

    Might well be the case that they don't want the hassle of going to court and so compromise, especially if they don't think their in-house legal team can handle it in which case they would have to spend money on external solicitors which they could not recover even if they won. If it did go to the small claims court, it is a pretty informal process where you talk through your case with the judge and answer any questions, they do likewise and he decides.

    Basically comes down to how strong you think your case is that they formed a verbal contract and how much you think they are prepared to fight if you go legal. Plus whether it is worth the hassle if you can just go and find a new role anyway quite quickly.

+ Reply to Thread

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Content Relevant URLs by vBSEO 3.6.0 ©2011, Crawlability, Inc.