Quote:
Originally Posted by malvolio
Hang on. Your project is running late, they're bringing in extra resource to catch up and you want more money...?
Not saying it's your fault, but that's how the management will see it...
|
Urrrrm before you jump the gun
1) Its not
MY project. I am assigned to it but delays are due to signoffs for kit etc. If it was mine it would have been done ages ago without all the politics.
2) They have decided to "expand" the project ( i.e do more than what they intially had planned for ).
3) One contractor has already left hence replacing him + getting extra man as well.
So definitely not my fault and if it was i'd happily face the music. All I am saying is that I will have to train the noobs initially on the in and outs yet they would be getting more than I am.